August 21, 2013

Photos of the Brewery's Delivery & Installation


Its been many months in the making; a chronological album of the brewery equipment's delivery and installation.  The first of four tractor trailers arrived on Friday, June 21 and the last departed on Tuesday, June 25.  A rigging company came on July 1 to put all the tanks in place and turn them upright.

On July 8, two technicians arrived from the manufacturing company to assemble the pipes, pumps, valves and run electrical wires.  Now 7 weeks in and one tech down, we're just days from completion.

You can view the album on Google+