December 31, 2012

Happy New Year!

Blackthorn hasn't had much to report in the last few weeks, sorry guys.  We're still waiting for our builder's permit, until then there's not much to be done.

To wrap up 2012, Blackthorn:

  • Completed our business plan
  • Signed a lease for a 6,500 sq ft facility in Toms River, NJ
  • Partnered with a contractor
  • Obtained zoning and demolition permits
  • Began demo and received construction materials
  • Ordered a 25 barrel (775 gallon) brewhouse
  • Hired a brewer

We wish everyone a happy, healthy and exciting 2013.  Cheers!

 - Chip, Jacqui & Jason